Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

A.
when a stage plan has been prepared for
Answers
A.
when a stage plan has been prepared for
B.
at the beginning of
Answers
B.
at the beginning of
C.
when all the delivery steps have been completed within
Answers
C.
when all the delivery steps have been completed within
D.
at, or close to the end of,
Answers
D.
at, or close to the end of,
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 should be executed at, or close to the end of, a management stage. This timing allows for proper assessment of the stage's outcomes and preparation for the next stage, ensuring effective planning and reporting as required by the project board.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.