Which statement about time-driven controls is CORRECT?

A.
Time-driven controls are used for monitoring the progress of work packages and management stages
Answers
A.
Time-driven controls are used for monitoring the progress of work packages and management stages
B.
Time-driven controls take place when specific events happen
Answers
B.
Time-driven controls take place when specific events happen
C.
Time-driven controls are produced at the end of a stage
Answers
C.
Time-driven controls are produced at the end of a stage
D.
An exception report is a time-driven control
Answers
D.
An exception report is a time-driven control
Suggested answer: A

Explanation:

Time-driven controls in PRINCE2 are mechanisms that take place at predetermined intervals, such as end stage assessments or regular progress meetings, to ensure ongoing monitoring of the project's progression through its stages and the work being completed in work packages. They help in keeping the project on track by providing timely information on performance.

Reference: PRINCE2 7 Foundation Handbook and official training materials.