Question 198 - PRINCE2-7-Foundation discussion

Report
Export

How does the project plan help to support the 'manage by stages' principle?

A.
By identifying the customer's quality expectations
Answers
A.
By identifying the customer's quality expectations
B.
By defining products to ensure they are fit for purpose
Answers
B.
By defining products to ensure they are fit for purpose
C.
By identifying the major control points and milestones
Answers
C.
By identifying the major control points and milestones
D.
By estimating the timescales and costs of the project
Answers
D.
By estimating the timescales and costs of the project
Suggested answer: C

Explanation:

The project plan supports the 'manage by stages' principle in PRINCE2 by identifying major control points and milestones. These serve as points at which the project board can review progress and decide whether to continue with the project. This principle ensures that the project is manageable, controllable, and that decisions can be made with proper governance at each stage.

Reference: PRINCE2 Foundation Handbook, Manage by Stages section.