Which is a purpose of the 'managing a stage boundary' process?

A.
To enable the project board to approve the continuation of the project
Answers
A.
To enable the project board to approve the continuation of the project
B.
To exercise overall control over the project while delegating day-to-day management
Answers
B.
To exercise overall control over the project while delegating day-to-day management
C.
To assign work to be controlled by the team manager
Answers
C.
To assign work to be controlled by the team manager
D.
To define the work that needs to be done to deliver the project product
Answers
D.
To define the work that needs to be done to deliver the project product
Suggested answer: A

Explanation:

The purpose of the 'Managing a Stage Boundary' process in PRINCE2 is to prepare the next stage plan and provide the project board with key information needed to make a decision on whether to continue with the project. This process involves reviewing the current stage's progress and the overall project status to ensure project viability before moving forward.

Reference: PRINCE2 7 Foundation Handbook and official training materials.