Which is an objective of the 'starting up a project' process?

A.
To approve the initiation stage
Answers
A.
To approve the initiation stage
B.
To select the project mandate
Answers
B.
To select the project mandate
C.
To define the project quality management approach
Answers
C.
To define the project quality management approach
D.
To appoint the project management team
Answers
D.
To appoint the project management team
Suggested answer: D

Explanation:

One of the objectives of the 'Starting up a Project' process in PRINCE2 is to appoint the project management team. This step ensures that the necessary leadership and management roles are filled with competent individuals who can plan, oversee, and execute the project effectively from its initiation through to closure.

Reference: PRINCE2 7 Foundation Handbook and official training materials.