In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

A.
Directing a project
Answers
A.
Directing a project
B.
Managing product delivery
Answers
B.
Managing product delivery
C.
Managing a stage boundary
Answers
C.
Managing a stage boundary
D.
Initiating a project
Answers
D.
Initiating a project
Suggested answer: B

Explanation:

The process that links the Team Manager role with the PRINCE2 method in a commercial environment is 'Managing Product Delivery'. This process ensures that the project's products are created and delivered efficiently and effectively, aligning the work of the team with the overall project management approach.

Reference: PRINCE2 7 Foundation Handbook and official training materials.