What is a supplier of a PRINCE2 project responsible for?

A.
Providing the project mandate
Answers
A.
Providing the project mandate
B.
Providing resources to deliver the project outputs
Answers
B.
Providing resources to deliver the project outputs
C.
Establishing the project's governance
Answers
C.
Establishing the project's governance
D.
Realizing the benefits from the project
Answers
D.
Realizing the benefits from the project
Suggested answer: B

Explanation:

In PRINCE2, the supplier is responsible for providing the resources necessary for delivering the project outputs. This includes supplying the skills, materials, and technologies required to produce the products of the project, ensuring that these resources meet the project's specifications and quality requirements.

Reference: PRINCE2 7 Foundation Handbook and official training materials.