To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

A.
At the start of the project
Answers
A.
At the start of the project
B.
Throughout each stage
Answers
B.
Throughout each stage
C.
When a change is raised
Answers
C.
When a change is raised
D.
In exception situations
Answers
D.
In exception situations
Suggested answer: B

Explanation:

According to PRINCE2, the business justification, or the continued viability of the project, must be reviewed continually throughout each stage of the project. This ensures that the project remains aligned with business needs and objectives and that it is still worth pursuing in light of any developments or changes that may occur.

Reference: PRINCE2 7 Foundation Handbook and official training materials.