Question 227 - PRINCE2-7-Foundation discussion

Report
Export

As a minimum requirement for applying the risk theme, what must specifically be assessed?

A.
Whether a risk may cause the project to exceed its cost tolerance
Answers
A.
Whether a risk may cause the project to exceed its cost tolerance
B.
Whether a risk may affect the project-level quality tolerances
Answers
B.
Whether a risk may affect the project-level quality tolerances
C.
Whether a risk may impact the underlying technical assumptions
Answers
C.
Whether a risk may impact the underlying technical assumptions
D.
Whether a risk may alter the project's business justification
Answers
D.
Whether a risk may alter the project's business justification
Suggested answer: D

Explanation:

According to the PRINCE2 risk management approach, a minimum requirement for applying the risk theme is to assess whether a risk may alter the project's business justification. This assessment ensures that risks are identified, analyzed, and managed in relation to their potential impact on the project's ability to deliver its intended benefits and justify the investment.

Reference: = PRINCE2 7 Foundation handbook and online resources

Topic 3, Exam Pool C

asked 23/09/2024
Rachana Kesarkar
31 questions