What is an advantage of applying the 'learn from experience' principle?

A.
It allows the project board to delegate cost tolerances to the project manager
Answers
A.
It allows the project board to delegate cost tolerances to the project manager
B.
It allows the project team to fully understand their roles and responsibilities
Answers
B.
It allows the project team to fully understand their roles and responsibilities
C.
It allows the project manager to delegate time tolerances to the team managers
Answers
C.
It allows the project manager to delegate time tolerances to the team managers
D.
It allows the project team to identify improvements to be made during the project
Answers
D.
It allows the project team to identify improvements to be made during the project
Suggested answer: D

Explanation:

The 'learn from experience' principle in PRINCE2 encourages continuous learning and adaptation within the project team. By applying this principle, teams are able to capture and act upon lessons learned throughout the project, thereby identifying and implementing improvements in real-time, which can enhance project outcomes.

Reference: = PRINCE2 7 Foundation handbook and online resources