Question 229 - PRINCE2-7-Foundation discussion

Report
Export

Which is a purpose of the 'initiating a project' process?

A.
To produce a stage plan for each stage of a multi-stage project
Answers
A.
To produce a stage plan for each stage of a multi-stage project
B.
To enable the project board to decide whether it is worthwhile to initiate a project
Answers
B.
To enable the project board to decide whether it is worthwhile to initiate a project
C.
To provide a fixed point at which acceptance for the project product is confirmed
Answers
C.
To provide a fixed point at which acceptance for the project product is confirmed
D.
To enable an organization to understand the work needed to deliver the project's products
Answers
D.
To enable an organization to understand the work needed to deliver the project's products
Suggested answer: B

Explanation:

The primary purpose of the 'Initiating a Project' process in PRINCE2 is to provide a foundation for the project board to make an informed decision about whether it is worthwhile to proceed with the project. This process involves the development of a detailed Project Initiation Documentation that outlines the project's objectives, scope, constraints, and management strategies.

Reference: PRINCE2 7 Foundation Handbook and official training materials.