Which are objectives of the 'managing a stage boundary' process?

1. To control the link between the people managing the project and the people producing the products

2. To approve requests for change received during the completed stage

3. To provide information to the project board on the performance of the current stage

4. To review and, if necessary, update the project management team structure and role descriptions

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: C

Explanation:

The objectives of the 'Managing a Stage Boundary' process include providing the project board with information about the performance of the current stage and reviewing and updating the project management team structure and role descriptions if necessary. These objectives are critical to ensuring that the project adapts to any changes and continues to align with its objectives efficiently.

Reference: PRINCE2 7 Foundation Handbook and official training materials.