Which statement about the length of management stages in a project is CORRECT?

A.
A higher level of major risk will require a stage to be longer
Answers
A.
A higher level of major risk will require a stage to be longer
B.
Stage length is influenced by project board availability
Answers
B.
Stage length is influenced by project board availability
C.
A higher level of major risk will require a stage to be shorter
Answers
C.
A higher level of major risk will require a stage to be shorter
D.
Use of management stages represents a time driven control
Answers
D.
Use of management stages represents a time driven control
Suggested answer: B

Explanation:

The length of management stages in a PRINCE2 project can be influenced by the availability of the project board to review and approve key decisions at stage boundaries. This ensures that stages are planned around when decision-makers can participate and provide necessary guidance or approvals.

Reference: = PRINCE2 7 Foundation handbook and online resources