Question 259 - PRINCE2-7-Foundation discussion
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits
A.
1 and 2
B.
2 and 3
C.
3 and 4
D.
1 and 4