According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

A.
Project board, project manager and project assurance roles
Answers
A.
Project board, project manager and project assurance roles
B.
Directing, managing and delivering levels
Answers
B.
Directing, managing and delivering levels
C.
Business, user and supplier interests
Answers
C.
Business, user and supplier interests
D.
Corporate, programme management or the customer parties
Answers
D.
Corporate, programme management or the customer parties
Suggested answer: C

Explanation:

According to the 'defined roles and responsibilities' principle in PRINCE2, the project management team must represent the business, user, and supplier interests. This ensures that all critical viewpoints are considered in decision-making processes, aligning the project outcomes closely with organizational needs and stakeholder expectations.

Reference: PRINCE2 Foundation Handbook, Defined Roles and Responsibilities section.