Which is a minimum requirement for applying the risk theme?

A.
Threats must be assessed for their impact on the viability of the project
Answers
A.
Threats must be assessed for their impact on the viability of the project
B.
A single role that is responsible for all risks must be defined
Answers
B.
A single role that is responsible for all risks must be defined
C.
The PRINCE2 risk management procedure must be followed
Answers
C.
The PRINCE2 risk management procedure must be followed
D.
Team managers must maintain their own risk registers
Answers
D.
Team managers must maintain their own risk registers
Suggested answer: C

Explanation:

A minimum requirement for applying the Risk Theme in PRINCE2 is to follow the PRINCE2 risk management procedure. This procedure includes the systematic process of identifying, assessing, and controlling project risks, ensuring that risks are managed proactively throughout the project.

Reference: PRINCE2 7 Foundation Handbook and official training materials.