Which is a minimum requirement for applying the risk theme?
A.
Threats must be assessed for their impact on the viability of the project
B.
A single role that is responsible for all risks must be defined
C.
The PRINCE2 risk management procedure must be followed
D.
Team managers must maintain their own risk registers