Which is an objective of the 'directing a project' process?

A.
To review and approve a project mandate
Answers
A.
To review and approve a project mandate
B.
To ensure corporate or programme management has an interface to the project
Answers
B.
To ensure corporate or programme management has an interface to the project
C.
To define how risks, issues and changes will be managed
Answers
C.
To define how risks, issues and changes will be managed
D.
To obtain approval for completed products
Answers
D.
To obtain approval for completed products
Suggested answer: B

Explanation:

One of the objectives of the 'Directing a Project' process in PRINCE2 is to ensure that there is a clear interface between the project and corporate or programme management. This process enables strategic oversight and decision-making, aligning the project with broader organizational objectives and governance frameworks.

Reference: PRINCE2 7 Foundation Handbook and official training materials.