Question 264 - PRINCE2-7-Foundation discussion

Report
Export

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.
To identify responses to risks documented in the business case
Answers
A.
To identify responses to risks documented in the business case
B.
To identify information about the project environment and objectives
Answers
B.
To identify information about the project environment and objectives
C.
To identify the roles to be involved in risk management activities
Answers
C.
To identify the roles to be involved in risk management activities
D.
To identify uncertainties that may impact on the delivery of the project objectives
Answers
D.
To identify uncertainties that may impact on the delivery of the project objectives
Suggested answer: D

Explanation:

The purpose of the 'Identify the Risks' step within the recommended risk management procedure is to identify uncertainties that may impact the achievement of project objectives. This step involves recognizing potential issues and challenges that could threaten the project's success, enabling proactive management and mitigation strategies.

Reference: PRINCE2 7 Foundation Handbook and official training materials.