Question 264 - PRINCE2-7-Foundation discussion
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
A.
To identify responses to risks documented in the business case
B.
To identify information about the project environment and objectives
C.
To identify the roles to be involved in risk management activities
D.
To identify uncertainties that may impact on the delivery of the project objectives