Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

A.
Communication management approach
Answers
A.
Communication management approach
B.
Quality management approach
Answers
B.
Quality management approach
C.
Project plan
Answers
C.
Project plan
D.
Initiation stage plan
Answers
D.
Initiation stage plan
Suggested answer: D

Explanation:

The Initiation Stage Plan specifies how the project board should approve management products produced during the 'initiating a project' process. It sets out the plan for the initiation stage, detailing the management and control of this stage, including how deliverables are to be reviewed and approved.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources