Which product describes the method the project will use to engage with corporate, programme management or the customer?

A.
Quality management approach
Answers
A.
Quality management approach
B.
Communication management approach
Answers
B.
Communication management approach
C.
Change control approach
Answers
C.
Change control approach
D.
Benefits management approach
Answers
D.
Benefits management approach
Suggested answer: B

Explanation:

The Communication Management Approach describes the means and frequency of communication to parties both within and outside the project. It outlines how the project will engage with stakeholders, including corporate, programme management, or the customer. This approach ensures that necessary information is provided to the right stakeholders at the right time.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources