Question 267 - PRINCE2-7-Foundation discussion

Report
Export

Which is one of the six aspects of project performance to be managed?

A.
Efficiency
Answers
A.
Efficiency
B.
Timescales
Answers
B.
Timescales
C.
Estimate
Answers
C.
Estimate
D.
Work
Answers
D.
Work
Suggested answer: B

Explanation:

One of the six aspects of project performance to be managed according to PRINCE2 is 'timescales'. Managing timescales involves planning and controlling when products will be delivered and ensuring the project remains within the agreed schedule.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources