Question 271 - PRINCE2-7-Foundation discussion
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.
A.
are able to overturn the decisions of
B.
must be accountable to
C.
should support
D.
report to the project board and
Your answer: