Question 271 - PRINCE2-7-Foundation discussion

Report
Export

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

A.
are able to overturn the decisions of
Answers
A.
are able to overturn the decisions of
B.
must be accountable to
Answers
B.
must be accountable to
C.
should support
Answers
C.
should support
D.
report to the project board and
Answers
D.
report to the project board and
Suggested answer: C

Explanation:

Project assurance personnel should support the project manager by providing an independent view on the progress and performance of the project, ensuring that it adheres to the project plan and meets its objectives without directly managing any of the project activities.

Reference: = PRINCE2 7 Foundation handbook and online resources