Question 270 - PRINCE2-7-Foundation discussion

Report
Export

What is a goal of the 'implement' step within the recommended risk management procedure?

A.
To prepare specific management responses to identified risks
Answers
A.
To prepare specific management responses to identified risks
B.
To monitor the effectiveness of actioned risk responses
Answers
B.
To monitor the effectiveness of actioned risk responses
C.
To estimate the risk to the project in terms of probability and impact
Answers
C.
To estimate the risk to the project in terms of probability and impact
D.
To communicate information related to the risks faced by the project
Answers
D.
To communicate information related to the risks faced by the project
Suggested answer: A

Explanation:

The goal of the 'implement' step within the recommended risk management procedure in PRINCE2 is to prepare specific management responses to the identified risks. This involves developing strategies to enhance opportunities and reduce threats to the project's objectives, ensuring that appropriate responses are ready for implementation.

Reference: = PRINCE2 7 Foundation handbook and online resources