Question 269 - PRINCE2-7-Foundation discussion

Report
Export

Which role is responsible for appointing the senior user in a project that is independent from a program?

A.
The project manager
Answers
A.
The project manager
B.
The executive
Answers
B.
The executive
C.
Corporate, program management or the customer
Answers
C.
Corporate, program management or the customer
D.
Project assurance
Answers
D.
Project assurance
Suggested answer: C

Explanation:

In PRINCE2, the role responsible for appointing the Senior User, as well as other key project roles such as the Executive and the Senior Supplier, is typically taken by someone from corporate or program management, or the customer. This aligns with the principle of clearly defined roles and responsibilities, ensuring that the project has clear governance and accountability. The Senior User is appointed to represent the interests of all those who will use the project's products, who will benefit from the outcomes, and those whose work might be impacted by the change.

Reference: PRINCE2 Foundation Manual