Question 278 - PRINCE2-7-Foundation discussion
Which is a minimum requirement for applying the organization theme?
A.
The project's approach to engaging with its stakeholders must be defined
B.
Roles must be combined to reduce the number of individuals needed on the project
C.
During a procurement the senior supplier must be appointed from the customer organization
D.
The project team must change at each end stage of the project life cycle