Why is it necessary to apply the 'defined roles and responsibilities' principle?
A.
Because the people involved in a project should know what is expected of them
B.
Because the project management team should be cross-functional
C.
Because the user and supplier interests should be involved on a need-to-know basis
D.
Because the project manager should represent all the stakeholders of the project
Your answer: