According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

A.
After the executive has been appointed
Answers
A.
After the executive has been appointed
B.
When authorized by the corporate, programme management or the customer
Answers
B.
When authorized by the corporate, programme management or the customer
C.
Before work to start the project commences
Answers
C.
Before work to start the project commences
D.
When an organization produces its business plans
Answers
D.
When an organization produces its business plans
Suggested answer: C

Explanation:

According to the 'continued business justification' principle in PRINCE2, a justifiable reason for a project is required before any work to start the project begins. This ensures that projects are initiated only when there is a clear business need, aligned with organizational objectives, and there is an expectation of value creation. The business case is developed during the initial stages of the project and is maintained and reviewed throughout the project lifecycle.