What is the change authority role permitted to authorize?

A.
Risks to the project
Answers
A.
Risks to the project
B.
Adjustments to the limits on the change budget
Answers
B.
Adjustments to the limits on the change budget
C.
Changes to stage tolerance
Answers
C.
Changes to stage tolerance
D.
Changes to the project that do not exceed a defined budget
Answers
D.
Changes to the project that do not exceed a defined budget
Suggested answer: D

Explanation:

The role of the change authority in PRINCE2 is to authorize changes within the project that do not exceed a predefined budget. This role is designated to ensure that any change proposals are evaluated and approved without exceeding the allocated budget for changes, thereby maintaining control over project costs and scope.

Reference: PRINCE2 Foundation Manual