Question 284 - PRINCE2-7-Foundation discussion
Which is a minimum requirement for applying the change theme?
A.
To identify whether an issue affects the continuation of the project
B.
To ensure each change is managed as an exception
C.
To produce a breakdown of the products to be produced
D.
To tailor all changes to improve the quality of the project