Question 285 - PRINCE2-7-Foundation discussion

Report
Export

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

A.
benefits, change, risk,
Answers
A.
benefits, change, risk,
B.
benefits, quality, risk,
Answers
B.
benefits, quality, risk,
C.
change, quality, risk,
Answers
C.
change, quality, risk,
D.
benefits, change, quality,
Answers
D.
benefits, change, quality,
Suggested answer: B

Explanation:

The six aspects of project performance to be managed, as outlined in PRINCE2, are benefits, costs, timescales, scope, quality, and risk. Managing these aspects helps ensure that the project delivers its intended outputs while adhering to predetermined constraints and achieving desired outcomes.

Reference: = PRINCE2 7 Foundation handbook and online resources