Question 287 - PRINCE2-7-Foundation discussion
What should the benefits management approach define?
A.
What actions will be taken to ensure the project's outcomes are achieved
B.
What will be used to record the effectiveness of the project's approaches
C.
How the project has progressed against its plans
D.
The suitability of the project management team structure