Question 288 - PRINCE2-7-Foundation discussion

Report
Export

Who is responsible for documenting any tailoring of the business case theme?

A.
Executive
Answers
A.
Executive
B.
Business project assurance
Answers
B.
Business project assurance
C.
Project manager
Answers
C.
Project manager
D.
Corporate management
Answers
D.
Corporate management
Suggested answer: C

Explanation:

In PRINCE2, the responsibility for documenting any tailoring of the Business Case theme, along with other themes, generally falls to the Project Manager. This includes documenting how the theme is being applied in a particular project context, ensuring the approach remains appropriate and meets the project's requirements.

Reference: PRINCE2 Foundation Manual