Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

A.
delivery step
Answers
A.
delivery step
B.
benefit
Answers
B.
benefit
C.
delivery stage
Answers
C.
delivery stage
D.
team plan
Answers
D.
team plan
Suggested answer: C

Explanation:

The 'Controlling a Stage' process in PRINCE2 is used to manage and control each 'delivery stage' of a project. This process focuses on the day-to-day management of the project stages, ensuring that the project remains within its agreed tolerances and effectively addressing issues as they arise.

Reference: PRINCE2 Foundation Manual