Question 290 - PRINCE2-7-Foundation discussion
What is documented in the project plan to support the 'manage by exception' principle?
A.
The project's tolerances for cost and time
B.
A project product's quality criteria
C.
The expected project benefits
D.
Activities to mitigate project risks