Which is an assumption about the PRINCE2 customer/supplier environment?

A.
The supplier will pay for the project
Answers
A.
The supplier will pay for the project
B.
The customer will provide the resources to deliver the products
Answers
B.
The customer will provide the resources to deliver the products
C.
The customer will specify the desired result
Answers
C.
The customer will specify the desired result
D.
The supplier will tailor the project's application of PRINCE2
Answers
D.
The supplier will tailor the project's application of PRINCE2
Suggested answer: C

Explanation:

A fundamental assumption in the PRINCE2 framework regarding the customer/supplier environment is that the customer will specify the desired result. This assumption underlines the relationship where the customer defines what they want to achieve from the project, and the supplier provides the resources and expertise to deliver the project's outputs that meet these specifications.