Question 292 - PRINCE2-7-Foundation discussion
Which is a purpose of the 'directing a project' process?
A.
To create and authorize the project mandate
B.
To ensure that work on products allocated to the team is authorized and agreed
C.
To control the day-to-day running of the project
D.
To delegate day-to-day management of the project to the project manager
Your answer: