How are team managers involved in tailoring PRINCE2 suit the project?

A.
Team managers are accountable for the tailoring of the work packages
Answers
A.
Team managers are accountable for the tailoring of the work packages
B.
Team managers may advice on tailoring to improve the management of work packages
Answers
B.
Team managers may advice on tailoring to improve the management of work packages
C.
Team managers should not be involved in tailoring PRINCE2
Answers
C.
Team managers should not be involved in tailoring PRINCE2
D.
Team managers should document the tailoring of the work packages
Answers
D.
Team managers should document the tailoring of the work packages
Suggested answer: B

Explanation:

While team managers in PRINCE2 are primarily responsible for the production of the work packages assigned to them, they may also provide valuable advice on tailoring the methodology to better manage these work packages within the specific context of the project. Their practical experience and direct involvement with project delivery can offer insights into how PRINCE2 can be adapted to enhance efficiency and effectiveness at the team level.

Reference: PRINCE2 Foundation Manual

=========================