Question 296 - PRINCE2-7-Foundation discussion
How are team managers involved in tailoring PRINCE2 suit the project?
A.
Team managers are accountable for the tailoring of the work packages
B.
Team managers may advice on tailoring to improve the management of work packages
C.
Team managers should not be involved in tailoring PRINCE2
D.
Team managers should document the tailoring of the work packages