How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?

A.
The work packages are defined by the team manager and supported by a team plan
Answers
A.
The work packages are defined by the team manager and supported by a team plan
B.
the work packages provided by the project manager are agreed by the team manager
Answers
B.
the work packages provided by the project manager are agreed by the team manager
C.
The team plans are checked by project assurance against the work packages
Answers
C.
The team plans are checked by project assurance against the work packages
D.
The stage plan covering the work packages is created with input from the team manager
Answers
D.
The stage plan covering the work packages is created with input from the team manager
Suggested answer: B

Explanation:

In the 'Managing Product Delivery' process of PRINCE2, the team manager's perspective is considered by ensuring that work packages provided by the Project Manager are agreed upon by the Team Manager. This agreement includes understanding the requirements, scope, and criteria of the work packages, thus ensuring that the team manager is fully informed and agrees with what needs to be delivered.