Question 298 - PRINCE2-7-Foundation discussion

Report
Export

What must be produced to meet the minimum requirements when applying the change theme?

A.
A change budget for the analysis of change
Answers
A.
A change budget for the analysis of change
B.
Records of the decisions made on all issues
Answers
B.
Records of the decisions made on all issues
C.
Documents recording the version of each product
Answers
C.
Documents recording the version of each product
D.
Status reports on all products being produced
Answers
D.
Status reports on all products being produced
Suggested answer: B

Explanation:

To meet the minimum requirements when applying the change theme in PRINCE2, it is necessary to maintain records of the decisions made on all issues. This includes documenting how each issue was addressed and any subsequent changes made to project plans or products. This record-keeping is crucial for traceability, accountability, and ensuring that decisions are aligned with project objectives and governance.

Reference: PRINCE2 Foundation Manual