What must be done for a project to be a PRINCE2 project?

A.
The project must form part of a programme or portfolio
Answers
A.
The project must form part of a programme or portfolio
B.
The project must meet the minimum requirements for applying the themes
Answers
B.
The project must meet the minimum requirements for applying the themes
C.
The project must use the recommended approach to planning
Answers
C.
The project must use the recommended approach to planning
D.
The project roles must be combined wherever possible
Answers
D.
The project roles must be combined wherever possible
Suggested answer: B

Explanation:

For a project to be considered a PRINCE2 project, it must meet the minimum requirements for applying the seven PRINCE2 themes. These themes (Business Case, Organization, Quality, Plans, Risk, Change, and Progress) provide a framework for managing the project and ensuring that it is conducted in a systematic, consistent manner that is aligned with PRINCE2 principles.

Reference: = PRINCE2 7 Foundation handbook and online resources