List of questions
Related questions
Question 304 - PRINCE2-7-Foundation discussion
The project manager has created a list of tasks to produce the project's products.
Which step of the 'organizational design and development' technique should be informed ty this 1st?
A.
Design the project ecosystem
B.
Understand the organizational ecosystem
C.
Manage the ongoing changes to the project ecosystem
D.
Develop the project ecosystem
Your answer:
0 comments
Sorted by
Leave a comment first