Question 304 - PRINCE2-7-Foundation discussion

Report
Export

The project manager has created a list of tasks to produce the project's products.

Which step of the 'organizational design and development' technique should be informed ty this 1st?

A.
Design the project ecosystem
Answers
A.
Design the project ecosystem
B.
Understand the organizational ecosystem
Answers
B.
Understand the organizational ecosystem
C.
Manage the ongoing changes to the project ecosystem
Answers
C.
Manage the ongoing changes to the project ecosystem
D.
Develop the project ecosystem
Answers
D.
Develop the project ecosystem
Suggested answer: C

Explanation:

In PRINCE2, the management of ongoing changes to the project ecosystem involves adapting the project's approach and scope based on real-time information and challenges that arise during the lifecycle of the project. This step is critical when new tasks or changes in tasks are identified, as outlined by the project manager. This ensures that the project remains aligned with its intended outcomes and can adapt to internal and external influences effectively.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation