Which is 3 purpose of the 'plans! practice?

A.
To enable an event that requires project management consideration to be controlled
Answers
A.
To enable an event that requires project management consideration to be controlled
B.
To provide the standards against which the project products can be quality controlled
Answers
B.
To provide the standards against which the project products can be quality controlled
C.
To provide the basis of control against which a project's progress can be monitored
Answers
C.
To provide the basis of control against which a project's progress can be monitored
D.
To enable control of opportunities and threats, that could Impact on delivery of the business objectives
Answers
D.
To enable control of opportunities and threats, that could Impact on delivery of the business objectives
Suggested answer: C

Explanation:

The 'Plans' practice in PRINCE2 is essential for setting up the basis for project control. This includes monitoring, reporting, and responding to project progress in comparison to the planned objectives and outcomes. It ensures that the project stays on track in terms of scope, time, cost, quality, risk, and benefits, and provides a clear mechanism to gauge progress against the initial plan.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation