Question 312 - PRINCE2-7-Foundation discussion

Report
Export

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: B

Explanation:

The Communication Management Approach in PRINCE2 defines how information should be sent to interested parties and how often this information should be communicated. It includes details on the methods and frequency of communication necessary to engage stakeholders effectively and ensure that everyone who needs to be informed about the project has the right information at the right time.

Reference: PRINCE2 Foundation Manual