What is an advantage of dividing the project into stages?

A.
Detailed plans can be prepared closer to the time events will take place
Answers
A.
Detailed plans can be prepared closer to the time events will take place
B.
the project board can delegate management of the project to team managers
Answers
B.
the project board can delegate management of the project to team managers
C.
The project can be authorized by the project manager on a stage by stage basis
Answers
C.
The project can be authorized by the project manager on a stage by stage basis
D.
The project brief can be updated towards the end of each stage
Answers
D.
The project brief can be updated towards the end of each stage
Suggested answer: A

Explanation:

One of the advantages of dividing the project into stages, as advocated by PRINCE2, is that detailed plans can be prepared closer to the time events will take place. This allows planning to be based on more accurate, up-to-date information, improving the relevance and accuracy of the plans. This approach also allows for better response to changes and risks, as planning for later stages can adjust based on the outcomes and learnings from earlier stages.

Reference: PRINCE2 Foundation Manual