Question 314 - PRINCE2-7-Foundation discussion

Report
Export

Which is a benefit of using PRINCE2?

A.
It promotes consistency of project work and the ability to reuse project assets.
Answers
A.
It promotes consistency of project work and the ability to reuse project assets.
B.
It includes techniques for critical path analysis and earned value analysis
Answers
B.
It includes techniques for critical path analysis and earned value analysis
C.
It enables a project manager to be accountable for the success of a project
Answers
C.
It enables a project manager to be accountable for the success of a project
D.
It prevents any changes once the scope of a project has been agreed
Answers
D.
It prevents any changes once the scope of a project has been agreed
Suggested answer: A

Explanation:

PRINCE2 benefits organizations and project management by promoting consistency across project work and facilitating the reuse of project assets. This includes methodologies, processes, and lessons learned which enhance efficiency and effectiveness in managing projects, thereby contributing to consistent project success and resource optimization.

Reference: = PRINCE2 7 Foundation handbook and online resources