How does the 'managing product delivery' process achieve its purpose?
A.
By agreeing requirements for how project work should be undertaken
B.
By producing highlight reports to enable the project board to oversee the work
C.
By requiring the project manager to produce and monitor team plans
D.
By escalating issues and risks that cannot be resolved within stage tolerance