What is a risk actionee responsible for?
A.
Identifying risks to the project that might occur in their department
B.
Owning and authorizing the use of the risk budget to fund risk responses
C.
Managing, monitoring and controlling of all aspects of an assigned risk
D.
Carrying out a risk response action to respond to a particular risk