Which activity is part of the recommended risk management procedure?

A.
Allocating a budget to investigate issues
Answers
A.
Allocating a budget to investigate issues
B.
Reviewing risk management practices to ensure that they are performing effectively
Answers
B.
Reviewing risk management practices to ensure that they are performing effectively
C.
Sending information to stakeholders about risks to the projects
Answers
C.
Sending information to stakeholders about risks to the projects
D.
Resolving conflicts between the project and the programme board
Answers
D.
Resolving conflicts between the project and the programme board
Suggested answer: B

Explanation:

Part of the recommended risk management procedure in PRINCE2 includes regularly reviewing risk management practices to ensure they are effective. This activity involves evaluating the processes used for risk identification, assessment, and response to ensure that risks are being managed appropriately and that the procedures are fit for purpose.

Reference: PRINCE2 Foundation Manual