Which management product is used to record relationships between specialist products?

A.
Change control approach
Answers
A.
Change control approach
B.
Configuration item record
Answers
B.
Configuration item record
C.
Issue register
Answers
C.
Issue register
D.
Product status account
Answers
D.
Product status account
Suggested answer: B

Explanation:

The management product used to record relationships between specialist products in PRINCE2 is the Configuration Item Record. This record includes information on each product's status, version, and interrelationships, providing a comprehensive overview of how different project outputs are connected and managed.

Reference: PRINCE2 Foundation Manual