Which is a minimum requirement for applying the 'change' theme?

A.
Specify in the change control approach the means by which project products will be protected
Answers
A.
Specify in the change control approach the means by which project products will be protected
B.
Document the format and contents of the issue register
Answers
B.
Document the format and contents of the issue register
C.
Produce issue reports to document the impact assessment for requests for change
Answers
C.
Produce issue reports to document the impact assessment for requests for change
D.
Delegate the change authority to the senior supplier(s) for supplier off-specifications
Answers
D.
Delegate the change authority to the senior supplier(s) for supplier off-specifications
Suggested answer: B

Explanation:

A minimum requirement for applying the 'change' theme in PRINCE2 is to document the format and contents of the issue register. This ensures that all issues, including requests for change, are captured systematically and managed appropriately throughout the project lifecycle.

Reference: = PRINCE2 7 Foundation handbook and online resources