Question 323 - PRINCE2-7-Foundation discussion
Which is a minimum requirement for applying the 'change' theme?
A.
Specify in the change control approach the means by which project products will be protected
B.
Document the format and contents of the issue register
C.
Produce issue reports to document the impact assessment for requests for change
D.
Delegate the change authority to the senior supplier(s) for supplier off-specifications
Your answer: